This project consisted of the installation of approximately 16.4 miles of 48-inch steel water transmission main by open cut and bore in San Antonio, TX. The project is critical for San Antonio Water System (SAWS) to have the capability of supplying water to rapidly developing areas of San Antonio and to recharge the SAWS Aquifer Storage and Recovery Facility.
Award Name
Pipeline Project
Company Name
American Spiralweld Pipe Company, LLC
Award Year
2022
Product Details
- WRIP Phase 2 - Pipeline Segment 2C & 3
- San Antonio Water System
- San Antonio, TX
Date Completed
August 1, 2022
Diameter
48"
Steel Tonnage Used
6200
Steel Thickness
.260"
Steel Fitting Type
AWWA C208