This project consisted of the installation of approximately 16.4 miles of 48-inch steel water transmission main by open cut and bore in San Antonio, TX.  The project is critical for San Antonio Water System (SAWS) to have the capability of supplying water to rapidly developing areas of San Antonio and to recharge the SAWS Aquifer Storage and Recovery Facility.

Award Name

Pipeline Project

Company Name

American Spiralweld Pipe Company, LLC

Award Year

2022

Product Details

  • WRIP Phase 2 - Pipeline Segment 2C & 3
  • San Antonio Water System
  • San Antonio, TX

Date Completed

August 1, 2022

Diameter

48"

Steel Tonnage Used

6200

Steel Thickness

.260"

Steel Fitting Type

AWWA C208