This chemical storage tank project scope included seven (07) shop built welded steel tanks for a new water purification facility in San Diego. All tanks were shop built, coated with a chemical- resistant heat cured coating prior to being shipped to and installed at the facility.

Two tanks were 9′ DIA x 24′ H with dished head roofs meant to store caustic soda. Three (03) tanks were 14′ DIA x 15’2″H with dished head roofs to hold sulfuric acid. The final two (02) tanks were smaller 5′ DIA x 6′ H Sulfuric Acid Day Tanks with dished head roofs.

Award Name

Special Fabrication

Company Name

Paso Robles Tank, Inc

Award Year

2024

Product Details

  • North County Pure Water Facility Project
  • City of San Diego
  • San Diego, CA, United States

Date Completed

December 1, 2024

Construction Standard

API 650

Overall Height

Column Height

Capacity

74,100

Steel Tonnage Used

58

Steel Thickness

3/8