This project scope covered the removal and replacement of a shovel-bottom floor in an existing Oily Waste Tank used to hold waste and bilge water from sea ships. Project further included cutting door sheet into the tank shell, removal and storage of a raker arm assembly, removal of corroded tank floor and sump drain, removal of all sub-grade materials to concrete containment, replacement of drain piping, sub-grade material, drain sump and new floor.
Complications included removal and replacement of the floor in the exact orientation and location in order to reuse the existing raker arm assembly with no conflicts. Hazardous material removal also required delicate attention to detail and great care.
Award Name
Repair, Modification, and Upgrade
Company Name
Paso Robles Tank, Inc
Award Year
2024
Product Details
- Oily Waste Tank LET 201 Rebottom
- NAVFAC Southwest
- San Diego, CA, United States
Date Completed
abril 19, 2025
Construction Standard
API 653
Overall Height
0.00
Column Height
0.00
Diameter
43' - 6 1/4"
Capacity
0.00
Steel Tonnage Used
8.5
Steel Thickness
1/4